Airport Runway Extension - Sargent

Airport Runway Extension

Client
Town of Rangeley
Location
Rangeley, Maine
Services Provided
General Contractor
Market

Key Facts

  • The reconstruction and extension of the Steven A. Bean Municipal Airport's runway began in 2018 with extending both ends with 400,000 yards of rock borrow. Approximately 75 feet of fill to extend the 14 end of the runway.
  • Approximately 2,500’ of Loon Lake Road was relocated to make room for the 32 end of the runway extension.
  • Sargent crews had 70 days to complete the extension of the runway, and have it reopened for aircraft.
  • The runway now extends 4300 LF and has new underdrain, subbase and base gravels, and pavement.