Stetson Mountain Wind Farm Phase 2

Danforth, Maine

Download PDF

Owner

First Wind
85 Wells Ave, Suite 305
Newton, MA 02459
(617) 964-3340

Project Type

Sitework for a Wind Farm - 17 Turbines

Engineer

FST / Stantec

Start / Finish

September 2009 - May 2010

Description / Significance

Sargent was the general site work contractor to construct the roads, drainage, turbine pad sites, substation site and overall infrastructure for the erection of 17 GE 1.5KW wind turbines. This project was phase 2 of the 2 phase project bringing the total operating turbines at this site to 55. Sargent also constructed the Phase 1 site infrastructure.

This project required approximately 227,000 cubic yards of rock and ledge excavation. 40,000 yards of gravel was placed and 96 acres of clearing was required for the project.