Charlottesville Airport – RW 21 Phase 3&4

Charlottesville, Virginia

Download PDF

Owner

Charlottesville-Albemarle Airport
100 Bowen Loop
Charlottesville, VA 22901
434-973-8342

Project Type

Runway Construction

Engineer

Delta Airport Consultants
9711 Farrar Court
Suite 100
Richmond, VA 23236
804-275-8301

Start / Finish

October 2012 - June 2014

Description / Significance

This runway extension included the following activities:

  • 300,000 cubic yards excavation
  • 400,000 cubic yards of rock excavation
  • 5,600 tons of P-401 pavement
  • 20,000 square feet Redi-Rock retaining wall
  • Airfield electrical & lighting
  • 1,855 linear feet of storm drain piping
  • Sediment basin construction
  • 17,800 square feet of pavement marking
  • 55 Acres seeding & mulching
  • Plantings
  • Fencing & Gates
  • Steel localizer platform